Taxiway A11 Rehabilitation

The Taxiway A11 repaving project will replace the current pavement in this area that is failing and replace it with new pavement, meeting the current design standards for the aircraft that use the A11 interstation. The project will also install in-pavement runway guard lights. This will increase safety during dark and low visibility conditions.

Map of King County International Airport-Boeing Field with Taxiway A11 highlighted
Map of King County International Airport-Boeing Field with Taxiway A11 highlighted
Closeup map showing construction plan for Taxiway A11
Closeup map showing Taxiway A11 work area

Objectives and Goals

  • Reduce FOD (Foreign Object Debris) generation
  • Improve safety
  • Increase the pavement life span
  • Complete the project as sustainably as possible

Schedule

  • Design: Completed first quarter 2024
  • Bidding: Second quarter 2024
  • Construction: Second and third quarter 2024

Public meetings

Thursday, March 28, 2024

Both sessions will cover the same information. Recordings will be posted to the airport website.