Project schedule
Houghton Transfer Station Roof Improvement and Mitigation Project
Schedule effective November 2010 (subject to change)
Dates* |
Action/Event |
June – December 2007 |
Environmental Review of the Project |
Nov. 30, 2007 |
SEPA Environmental Checklist and Determination of Non-Significance |
September 2008 |
Land Use Permit Obtained |
May 2009 – May 2010 |
Permitting Process |
February – June 2010 |
Construction Bid Process |
August 2, 2010 – January 24, 2011 |
Construction |
January 24, 2011 |
Construction completed; station reopens on weekdays to all customers. |