Skip to main content
King County logo
Pavement repair work.
Pavement repair work in south King County before anti-skid treatment is applied.

The Road Services Division identified 24 locations where epoxy and anti-skid material (high friction surface treatment - HFST) was applied in 2018 to increase traction for vehicles. Data shows that this treatment helps dramatically decrease the numbers of crashes.

Work at the project locations below took place between August - October, 2018.

2018 anti-skid treatment locations

2018 high friction surface treatment locations
2018 anti-skid treatment locations map PDF

Contact us

Brent Champaco
206-477-9094

Stay connected

Sign up for Road Alerts

Follow us on Twitter

Look at Twitter.

Find us on Facebook

Look at Facebook.

ROAD

EXTENT

SCHEDULED WORK

NORTHEAST

NE Lake Joy Road

750' curve located about 1,000' west of 342nd Avenue NE, beginning in the vicinity of house #33718

Completed 2018

                                   

NE Woodinville-Duvall Road & Avondale Road NE

500' of west leg, 150' of south leg & 200' of east leg

Completed 2018

SOUTH

46th Avenue S & S 382nd Street

250' curve at intersection of S 382nd Street and 46th Avenue S

Completed 2018

Green River Road S

500' curve between 28300 to 28500 block, in the vicinity of Mary Olson Farm

Completed 2018

S 272nd Street & Military Road S

300' of east leg two thru lanes

Completed 2018

S 282nd Street

Two 400' curves located between 46th Avenue S to 48th Avenue S

Dec. 10, 2018, 1:46 p.m. - Today's pavement surface repair work has completed. Learn more.

S 304th Street & 31st Avenue S

350' curve at intersection of 31st Avenue S and S 304th Street, west of 32nd Avenue S and northwest of Lake Dolloff

Completed 2018

SOUTHEAST

164th Avenue SE

500' curve located at about 1,100' north of Peter Grubb Road SE & SE 292nd Street, between house #28836 and #28824

Completed 2018

168th Way SE

300' curve located at intersection with SE 314th Street, between house #31416 and #31314

Completed 2018

Landsburg Road SE

500' curve located at intersection with SE Summit Landsburg Road

Completed 2018
            
           

SE 232nd Street

400' curve at intersection with 192nd Avenue SE, between house #23039 and #19223

Completed 2018  

SE 288th Street

520' curve located west of intersection with SR 169 (Maple Valley-Black Diamond Road)

Completed 2018

SE 452nd St & SE 456th Way

300' curve located at about 1,200' east of 228th Avenue SE, from house #23114 to #23205

Completed 2018

SE Green Valley Road

500' curve located between house #19004 and #19205

Completed 2018

SE Kent Kangley Road

500' curve located north of intersection with Kanaskat Kangley Road SE, east of house #27546

Completed 2018

SE Lake Walker Road

250' curve located at about 250' east of Cumberland Way SE, at intersection with 312th Avenue SE

Completed 2018

SE May Valley Road & Issaquah Hobart Road SE

250' of south leg and 200' of north leg

Completed 2018.

SE Mt Si Road

300' curve as it turns to the north into 452nd Avenue SE, between house #44942 and #13131

Completed 2018

SE Petrovitsky Road & 140th Avenue SE

200' to 250' at west, north and east legs

Completed 2018

SE Reinig Road

480' curve in the vicinity of house #42320 and about 1,200' west of 428th Avenue SE

Completed 2018

SE Retreat Kanaskat Road

700' curve south of intersection with SE Kent Kangley Road to house #27502

Completed 2018

SOUTHWEST

87th Avenue SW

400' curve located about 1,200' north of SW Ellisport Road, between house #20534 and #20407

Completed 2018

SW Cemetery Road

250' curve at intersection with 87th Avenue SW

Completed 2018

SW Ellisport Road

450' long curve located about 1,000' west of 87th Avenue SW

Completed 2018

Also see

  • Road resurfacing projects