King County to host meeting to update residents on South Park Bridge progress

Meeting will also detail revised construction schedule

King County will host a community meeting at 7 p.m. Thursday, Nov. 15 to update residents on the status of South Park Bridge construction. The meeting will be held at the South Park Neighborhood Center, 8201 10th  Ave. S., Seattle.

During the meeting, County engineers will review construction progress, including efforts to excavate new piers. The contractor, Kiewit Massman JV, has informed the County that this phase of work has taken longer than expected, which will shift the timeline for opening the bridge. The County and the contractor are now working on a revised construction schedule. The updated timeline for bridge completion should be announced in a few weeks.

Meanwhile, other elements of the project are moving forward. Major steel components for the new bridge have started arriving. Later this month demolition of portions of the old bridge will get underway.

During the meeting, engineers will provide more details about construction activities currently underway, share photos of recently completed excavation work and answer questions.

For more information about the meeting, contact Ashley DeForest, (206) 684-1154 or email her at ashley.deforest@kingcounty.gov.