Project milestones
Green River Stormwater Retrofit Planning Project
Data collection, analysis and modeling
|
|
Nov. 2010 | Project Management Core Team to hold all-team project workshop |
Jan. 2011 | Approve Quality Assurance Project Plan (956 Kb Acrobat pdf) (Task 1) |
Feb. 2011 | Coordinate with WRIA 9 (Task 3) |
Mar.2011 | Continuous monitoring could be extended through April, 2011. |
Apr. 2011 | Public project input and feedback meeting/workshop |
May 2011 | Complete and deliver Existing Data Review Report (Task 4) |
Sept. 2011 | Complete In-stream Flow and Water Quality Goals literature review (Task 6).
Complete survey of low-flow data (Task 5) |
Nov. 2011 | Host public meeting(s) on project status (Task 11)
Coordinate with WRIA 9 Forum (Task 3) |
Dec. 2011 | Complete New Flow Data Collection Report (Task 5) |
May 2013 | Complete and deliver In-Stream Flow and Water Quality Goals Report (Task 6)
Complete Watershed Modeling and Report (Task 7) |
Model analysis and output
|
|
Sept. 2013 | Complete SUSTAIN Modeling and Report (Task 8) |
Report preparation and delivery
|
|
Nov. 2012 | Host public meeting(s) on project status (Task 11)
Coordinate with WRIA 9 Forum (Task 3) |
Dec. 2013 | Deliver completed Watershed Retrofit Plan Report (Task 9) |
Model marketing & delivery
|
|
Nov. 2013 | Host public meeting(s) on project status (Task 11) and coordinate with WRIA 9 Forum (Task 3) |
Dec. 2013 | Complete project results presentation (Task 11).
Deliver completed Stormwater Retrofit Cost Estimate for Puget Sound and Report (Task 10) |
For more information about the Stormwater Retrofit Project, please contact Jim Simmonds, Project Manager, Science and Technical Support Section.