DDES yearly statistics archive: Permit processing performance measures
DDES Year 2003 permit processing performance summary
Building Services
KEY PERMITS* 2003 |
Target Days |
Total Permits |
Mutually Agreed Time Extension |
Average Days |
# within Target |
% within Target |
# outside Target |
| Residential Model Homes (Basics) |
90 |
1159 |
|
1.6 |
1159 |
100% |
0 |
| Residential Custom Homes |
90 |
586 |
|
46.8 |
538 |
91.8% |
48 |
| Residential Minor Additions |
15 |
265 |
|
9.9 |
212 |
80.0% |
53 |
| New Commercial Buildings |
120 |
44 |
|
103.0 |
32 |
72.7% |
12 |
| Multi-Family Housing |
120 |
12 |
|
151.8 |
4 |
33.3% |
8 |
| Commercial Tenant Improvements |
120 |
39 |
|
63.3 |
33 |
84.6% |
6 |
*Key permits are individual permit types that are considered representative of major construction groups.
ALL PERMITS BY CLOCK TARGET* 2003 |
Total Permits |
Mutually Agreed Time Extension |
Average Days |
# within Target |
% within Target |
# outside Target |
| All Building Permits with 15 day Target |
288 |
|
10.0 |
233 |
80.9% |
55 |
| All Building Permits with 40 day Target |
683 |
|
34.5 |
443 |
64.9% |
240 |
| All Building Permits with 90 day Target |
2194 |
|
19.2 |
2126 |
96.9% |
68 |
| All Building Permits with 120 day Target |
2492 |
|
13.3 |
2429 |
97.5% |
63 |
| Totals |
5657 |
|
|
5231 |
92.5% |
426 |
*Excludes less than 1% of permits that did not have targets assigned.
Land Use Services
KEY PERMITS* 2003 |
Target Days |
Total Permits |
Mutually Agreed Time Extension |
Average Days |
# within Target |
% within Target |
# outside Target |
| Conditional Use |
120 |
10 |
|
71 |
9 |
90.0% |
1 |
| Preliminary Plats |
150 |
20 |
|
142 |
12 |
60.0% |
8 |
| Preliminary Short Plats |
120 |
37 |
|
113 |
29 |
78.4% |
8 |
| Lot Line Adjustments |
120 |
51 |
|
35 |
48 |
94.1% |
3 |
| Right-of-Way |
120 |
38 |
|
43 |
33 |
86.8% |
5 |
| Clearing/Grading |
45 |
0 |
|
0 |
N/A |
N/A |
N/A |
| Clearing/Grading |
90 |
303 |
|
50 |
258 |
85.1% |
45 |
*Key permits are individual permit types that are considered representative of major construction groups.
ALL PERMITS BY CLOCK TARGET* 2003 |
Total Permits |
Mutually Agreed Time Extension |
Average Days |
# within Target |
% within Target |
# outside Target |
| All Land Use Permits with 45 day Target |
0 |
|
N/A |
N/A |
N/A |
|
| All Land Use Permits with 90 day Target |
305 |
|
49.0 |
260 |
85.2% |
45 |
| All Land Use Permits with 120 day Target |
289 |
|
79.0 |
234 |
81.0% |
55 |
| All Land Use Permits with 360 day Target |
0 |
|
0 |
N/A |
N/A |
N/A |
| Totals |
594 |
|
|
494 |
83.2% |
100 |
*Excludes less than 1% of permits that did not have targets assigned. |