DDES yearly statistics archive: Permit processing performance measures
DDES Year 2001 permit processing performance summary
Building Services
KEY PERMITS* 2001 |
Target Days |
Total Permits |
Mutually Agreed Time Extension |
Average Days |
# within Target |
% within Target |
# outside Target |
| Residential Model Homes (Basics) |
90 |
897 |
|
3.3 |
894 |
99.7% |
3 |
| Residential Custom Homes |
90 |
580 |
2 |
62.4 |
491 |
84.9% |
87 |
| Residential Minor Additions |
15 |
275 |
7 |
3.6 |
247 |
92.2% |
21 |
| New Commercial Buildings |
120 |
44 |
1 |
134.7 |
19 |
43.2% |
24 |
| Multi-Family Housing |
120 |
8 |
|
197.4 |
2 |
25.0% |
6 |
| Commercial Tenant Improvements |
120 |
47 |
|
21.4 |
47 |
100.0% |
0 |
*Key permits are individual permit types that are considered representative of major construction groups.
ALL PERMITS BY CLOCK TARGET* 2001 |
Total Permits |
Mutually Agreed Time Extension |
Average Days |
# within Target |
% within Target |
# outside Target |
| All Building Permits with 15 day Target |
304 |
7 |
3.3 |
282 |
92.8% |
15 |
| All Building Permits with 40 day Target |
774 |
|
49.7 |
406 |
52.5% |
368 |
| All Building Permits with 90 day Target |
2127 |
2 |
28.2 |
2002 |
94.1% |
123 |
| All Building Permits with 120 day Target |
1431 |
1 |
32.4 |
1306 |
91.3% |
124 |
| Totals |
4636 |
|
|
3996 |
86.2% |
630 |
*Excludes less than 1% of permits that did not have targets assigned.
Land Use Services
KEY PERMITS* 2001 |
Target Days |
Total Permits |
Mutually Agreed Time Extension |
Average Days |
# within Target |
% within Target |
# outside Target |
| Conditional Use |
120 |
15 |
|
208.0 |
3 |
20.0% |
12 |
| Preliminary Plats |
150 |
33 |
|
203 |
5 |
15.2% |
28 |
| Preliminary Short Plats |
120 |
33 |
|
240.8 |
5 |
15.2% |
28 |
| Lot Line Adjustments |
120 |
89 |
|
68.6 |
76 |
85.4% |
13 |
| Right-of-Way |
120 |
46 |
1 |
75.0 |
38 |
84.4% |
7 |
| Clearing/Grading |
45 |
424 |
1 |
51.0 |
308 |
72.6% |
115 |
| Clearing/Grading |
90 |
17 |
|
192.0 |
7 |
41.2% |
10 |
*Key permits are individual permit types that are considered representative of major construction groups.
ALL PERMITS BY CLOCK TARGET* 2001 |
Total Permits |
Mutually Agreed Time Extension |
Average Days |
# within Target |
% within Target |
# outside Target |
| All Land Use Permits with 45 day Target |
426 |
1 |
54.1 |
308 |
72.3% |
117 |
| All Land Use Permits with 90 day Target |
22 |
|
281.3 |
9 |
40.9% |
13 |
| All Land Use Permits with 120 day Target |
438 |
1 |
87.6 |
315 |
71.9% |
122 |
| All Land Use Permits with 360 day Target |
2 |
|
655.5 |
1 |
50.0% |
1 |
| Totals |
888 |
|
|
633 |
71.3% |
253 |
*Excludes less than 1% of permits that did not have targets assigned. |