Project summaryThis project includes replacement of existing roof systems (asphalt shingle and single ply membrane).Project schedule
| Feb. 2008 |
Bid |
| April 2008 |
Notice of Award |
| April 2008 |
Begin Construction |
| April 2008 |
Complete Construction |
Project budget$320,000Staff contact
Chris Erickson Project Manager, Facilities Management Division 201 S. Jackson St. #700 Seattle, WA 98104 chris.erickson@kingcounty.gov Phone: 206-263-0445 Fax: 206-293-6217
|