Project summaryThis project includes the demolition of the existing dilapidated pier. Salvageable decking and railing materials will be recycled for use elsewhere within the County and/or within Community Partnership Grant Projects.Project schedule
| Aug. 2008 |
Complete Construction |
Project budget$215,000Contractor and/or Consultant
Consultant: Parametrix, Inc.
Staff contact
Chris Erickson Project Manager, Facilities Management Division 201 S. Jackson St. #700 Seattle, WA 98104 chris.erickson@kingcounty.gov Phone: 206-263-0445 Fax: 206-293-6217
|