Project summaryThis project provides the desing and construction to convert the outfield of Baseball Field #1 and full infield and outfield of Baseball Field #2 to synthetic turf multi-use baseball / soccer fields for year round play.Project documentsProject is currently in the schematic design phase.Permits and environmental review
| Sept. 2007 |
All required documentation for permit submitted. |
Project schedule
| Aug. 2007 |
Design Complete |
| Sept. 2007 |
Submit Permit |
| Jan. 2008 |
Complete Construction / Bidding Documents |
April – July 2008 |
Bid and Award |
| Aug. 2008 |
Begin Construction |
Project budget$2,600,000Contractor and/or ConsultantConsultant: Bruce Dees and Associates Brian Patnode, Project Manager
Staff contact
Karan Soi Project Manager, Facilities Management Division 201 S. Jackson St. #700 Seattle, WA 98104 karan.soi@kingcounty.gov Phone: 206-263-7283 Fax: 206-293-6217
|