Project summaryProvide a continuous multi-purpose trail from the west entrance at Marymoor Park through Marymoor Park connecting to East Lake Sammamish Trial that is consistent with the King County vision and guidelines for the Regional Trail System.Permits and environmental review
| Nov. 2007 |
Submitted all documentation required for grading and shoreline permits |
Project schedule
| May 2007 |
Central alignment route approved by Parks |
| Aug. 2007 |
Design Complete |
| Nov. 2007 |
Submitted Permits |
| Aug. 2008 |
Begin Construction |
Project budget$1,500,000.00Contractor and/or ConsultantConsultant: Parametrix Inc. Jenny Bailey, Project ManagerStaff contact
Karan Soi Project Manager, Facilities Management Division 201 S. Jackson St. #700 Seattle, WA 98104 karan.soi@kingcounty.gov Phone: 206-263-7283 Fax: 206-293-6217
|