Project timeline by phase

Phase 1
Oct. 2007 Began Survey of 11 Mile Trail Corridor
Jan. 2008 Began Design of 11 Mile Trail Corridor
July 2008 Complete 30% Design Documents of the 11 Mile Trail Corridor


Phase 2
July 2008 Begin Phase 2 of the trail project, Design of the Redmond Segment.
Dec. 2008 Submit Project Permits
Feb. 2009 Complete Design of Redmond Trail Segment
Aug. 2009 Begin Construction of Redmond Trail Segment
Feb. 2010 Complete Construction of Redmond Trail Segment


Phase 3
March 2009 Begin Phase 3 of the trail project, Design of the Issaquah Trail Segment
Aug. 2010 Begin Construction of the Issaquah Trail Segment
April 2010 Complete Construction of Issaquah Trail Segment


Phase 4
Jan. 2010 Begin Phase 4 of the trail project, Design of the North Sammamish Trail Segment
Aug. 2011 Begin Construction of the North Sammamish Trail Segment
July 2011 Complete Construction of the North Sammamish Trail Segment


Phase 5
Oct. 2011 Begin Phase 5 of the trail project, Design of the South Sammamish Trail Segment
Jan. 2012 Begin Construction of the South Sammamish Trail Segment
July 2013 Complete Construction of the South Sammamish Trail Segment




ESLT Project Schedule Chart

elst_project_schedule_small