Project timeline by phase
| Phase 1 |
| Oct. 2007 |
Began Survey of 11 Mile Trail Corridor |
| Jan. 2008 |
Began Design of 11 Mile Trail Corridor |
| July 2008 |
Complete 30% Design Documents of the 11 Mile Trail Corridor |
| Phase 2 |
| July 2008 |
Begin Phase 2 of the trail project, Design of the Redmond Segment. |
| Dec. 2008 |
Submit Project Permits |
| Feb. 2009 |
Complete Design of Redmond Trail Segment |
| Aug. 2009 |
Begin Construction of Redmond Trail Segment |
| Feb. 2010 |
Complete Construction of Redmond Trail Segment |
| Phase 3 |
| March 2009 |
Begin Phase 3 of the trail project, Design of the Issaquah Trail Segment |
| Aug. 2010 |
Begin Construction of the Issaquah Trail Segment |
| April 2010 |
Complete Construction of Issaquah Trail Segment |
| Phase 4 |
| Jan. 2010 |
Begin Phase 4 of the trail project, Design of the North Sammamish Trail Segment |
| Aug. 2011 |
Begin Construction of the North Sammamish Trail Segment |
| July 2011 |
Complete Construction of the North Sammamish Trail Segment |
| Phase 5 |
| Oct. 2011 |
Begin Phase 5 of the trail project, Design of the South Sammamish Trail Segment |
| Jan. 2012 |
Begin Construction of the South Sammamish Trail Segment |
| July 2013 |
Complete Construction of the South Sammamish Trail Segment |
|
|
|