The East Lake Sammamish Trail (ELST) project includes design and construction of an alternative non-motorized transportation corridor and a multi-use recreational trail along 11 miles of the former Burlington Northern Santa Fe railroad corridor on the east side of Lake Sammamish. The trail will provide access to recreation, employment, and retail center in the Cities of Redmond, Sammamish, and Issaquah and complete a link in the King County regional trails system.
As described in the Project History, the development of the trail is occurring in two phases:
Phase 1, Interim Use Trail : The Redmond and Issaquah sections of the Interim Use Trail, were completed and opened in March, 2004. Construction of the last segment of the Interim Use Trail through the City of Sammamish was completed and opened in March, 2006. The Interim use Trail is now approximately 11 miles in length, beginning at Gilman Boulevard in Issaquah and ending north of NE 70th Street in Redmond. More information...
The proposed Master Plan Trail will be multi-use to accommodate use by pedestrians, non-motorized wheeled vehicles, and equestrians. The propsed Master Plan Trail will be located in the same general corridor as the Interim Use Trail. The basic features of the Master Plan Trail include:
The project documents section contains the following records:
Project maps are available on their own page.
Parking, access points and restrooms along the trail (PDF, 728KB)
| Sept. 2007 | Submitted Final Environmental Impact Statement (FEIS) to WSDOT and FHWA - Pending Approval |
December 2008 |
Submitted National Historic Preservation Act (Section 106) to WSDOT and FHWA - Approved |
| August 2008 | Submitted Air Lease Agreement to WSDOT for portion of trail through the SR 520 and SR202 Rights-of Way - Pending Approval |
| Jan 2009 | Submitted Permit Application to City of Redmond for Redmond Trail Segment - Pending Approval |
| December 2009 | Issue Final EIS |
| January 2010 | Issue NEPA Record of Decision |
| January 2010 | Issue SEPA Notice of Action Taken |
| April 2010 | Submit Nationwide Permit (Section 404) to US Army Corps of Engineers for Issaquah Trail Segment |
| April 2010 | Submit Clean Water Act (Section 401) Water Quality Certification for Issaquah Trail Segment |
| Project timeline by phase | |
| Jan. 2008 | Begin Design of 11 Mile Trail Corridor |
| July 2008 | Complete 30% Design Documents of 11 Mile Trail Corridor |
| Dec 2008 | Complete 60% Design Documents for Redmond Trail Segment |
| Jan 2009 | Submit Conditional Use Permit Application to City of Redmond for Redmond Trail Segment |
| July 2009 | Complete Design Documents for Redmond Trail Segment |
| February 2010 | Advertise for Construction of Redmond Trail Segment |
| July 2010 | Begin Construction of Redmond Trial Segment |
| April 2011 | Complete Construction of Redmond Trail Segment |
| July 2009 | Begin Design of Issaquah Trail Segment |
| February 2010 | 60% Design Documents for Issaquah Trail Segment |
| May 2010 | Submit Conditional Use Permit Application to City of Issaquah for Issaquah Trail Segment |