Burke Gilman Trail Redevelopment Project Citizens Advisory Group
90% Design Presentation Tuesday, October 23, 2007 7:00 p.m. Lake Forest Park City Hall
King County has completed the 90% design milestone for the Burke-Gilman Trail Redevelopment Project. The trail design includes recommendations by the CAG, and comments from the public. As previously committed to the CAG, King County will present the 90% design to the committee.
| 7:00 p.m. |
Welcome/Overview --Terry Reckord, MacLeod Reckord |
| 7:05 p.m. |
Status Report --Gina Auld, King County |
| 7:10 p.m. |
Presentation of 90% Design --Terry Reckord, Design Team |
| 8:10 p.m. |
Discussion/Comment |
| 8:40 p.m. |
Schedule/Next Steps for the Redevelopment Project --Gina Auld |
| 8:55 p.m. |
Wrap-up and Adjourn | |