Project summaryThis project provides new, suicide-proof, easily cleaned HVAC air grilles in inmate areas, thereby helping to ensure appropriate levels of supply and return air to inmates. Ductwork connecting to the grilles will be modified to accommodate the new grille design. The original project consisted of two separate projects – KCCF Air Gilles and KCCF Duct Risers – which have been combined into a single project.Project schedule
| Jan. 2008 |
Begin consultant selection |
| March 2008 |
Begin design |
| June 2008 |
Begin bidding and permits |
| Sept. 2008 |
Begin construction |
| April 2008 |
Complete construction |
Project budget$696,000Staff contact