Project summaryFrom the guidelines of the District Court Facilities Master Plan, this project will separate zones of circulation into public, private, and, if feasible, secured zones. Card reader access will be added at existing main entrance door(s) and at interior doors separating private and secured zones from the public. Duress alarms and controllers will also be added or replaced. The facilities included in this project are; Southwest District Court, Northeast District Court, Shoreline District Court, Issaquah District Court and the Office of the Presiding Judge within the King County Courthouse.Project schedule
| May – June 2008 |
Pre-design and consultant selection |
| July 2008 |
Schematic design and design development |
| Aug. 2008 |
Construction drawings |
| Sept. – Nov. 2008 |
Bid and advertising |
| Dec. 2008 – March 2009 |
Construction |
| April – May 2009 |
Project closeout |
Project budget$353,321Staff contact
Denise Thompson Project Technician, Facilities Management Division 500 4th Ave Rm 320 Seattle, WA 98104 denise.thompson@kingcounty.gov Phone: 206.296.0552 Fax: 206.296.0186
|