Project summary

This project provides a new water booster pump system which will increase domestic water volumes / pressures at Floors 10, 11 and 12 at the Courthouse.

Project schedule

March 2007 Begin pre-design
March 2007 Begin consultant selection
April 2007 Begin design
Aug. 2007 Begin construction
April 2008 Complete construction

Project budget

$70,000

Staff contact

Stephen Swinburne
Capital Project Manager, Facilities Management Division