Project summaryThis project provides analyses of the Courthouse’s HVAC systems, recommendations to adjust, repair and replace HVAC systems and construction to remedy all HVAC anomolies. The final phase during construction will be to adjust and balance all hydronic and air HVAC systems.Project schedule
| June 2006 |
Begin pre-design |
| Oct. 2006 |
Begin HVAC study |
| Jan. 2008 |
construBegin HVAC retro-commissioningction |
| May 2008 |
Begin design |
| Jan. 2009 |
Begin bidding and permits |
| April 2009 |
Begin construction |
| March 2010 |
Complete construction |
Project budget$551,200Staff contact