Flow chart, Step 3: Property clean-up
  1. Property owner is complying with the requirements of the Decontamination Order. Property owner hires a Washington State Certified Decontamination Contractor.

  2. Property owner's contractor sends Clean-Up Work Plan to Public Health for review.
    • Is the Clean-Up Work Plan OK? (Yes or No):

      • Yes, Clean-Up Work Plan is sufficient. Next steps:
        • Send Acceptance Letter to Contractor
        • Oversee decontamination
        • Following completion of clean-up activities, contractor submits final report to Public Health for review

      • No, Clean-Up Work Plan is not OK. Send Revision Request Letter to Contractor.

    • Is Final Report OK? (Yes or No):

      • Yes, Final Report is OK. Release of Decontamination Order is sent to all parties and recorded at King County Division of Records and Elections.

      • No, Final Report is not OK. Send Revision Request Letter to contractor.