skip to main content

For questions about the Wastewater Treatment Division website, please send an e-mail message or contact us at:

King Street Center
201 S. Jackson St., Suite 500
Seattle, WA 98104-3855
Phone: 206-684-1280
Fax: 206-684-1741
Telecommunication device for the deaf (TTY): 711

Get Directions to our office location in Seattle, Washington.

Staff Contacts

Puget Sound shoreline next to the West Point Treatment Plant, Seattle

Ballard Siphon replacement project

Project construction

February 9, 2012 Project Update

North site: Shoring installation is complete! After several weeks of site cleanup and preparation, crews will begin shaft excavation. 
El sitio del norte: ¡La instalación de la columna es completo! Después de varias semanas de preparación del sitio, los equipos comenzarán la excavación del eje.

South site: Shaft construction begins. Truck deliveries increase as equipment and materials are brought to the site.
El sitio del sur: La construcción del eje comienza. Aumentan las entregas de camiones como equipo y materiales son llevados al sitio.

View project update (PDF, February 9) 

Typical work hours: 7:00 a.m. – 6:00 p.m. weekdays
24-hour project hotline/Para más información*: 206-296-3848
  (*Señale su idioma y llamaremos a un intéprete. El servicio es gratuito.)

Project description

Ballard Siphon Project Map
Project map. Click map to enlarge view. Also available as PDF

Construction Photos at the North Site, January 30, 2012
Construction Photos at the North Site (PDF), January 30, 2012

 Pedestrian Detour Map
Pedestrian detour map
 (PDF), August 2011

To protect public health and the environment, King County is building a new 84-inch siphon pipe under Salmon Bay between the Ballard and Interbay areas of Seattle. The new siphon will be installed more than 120 feet underground and connect the Ballard Regulator Station at 5110 Shilshole Avenue Northwest in Ballard to the North Interceptor at West Commodore Way and 24th Avenue West intersection in Interbay (see project map).

After excavating vertical shafts at the Shilshole Avenue and Commodore Way sites, King County’s contractor will install a tunnel boring machine to bore a pipe corridor for the new siphon roughly 60 feet beneath Salmon Bay. The existing siphon will be cleaned out and relined as part of this project. Additional equipment supporting the new pipe will also be installed at the Ballard Regulator.

Project need

The new pipe is needed to accommodate growth in north Seattle. The new pipe replaces two 36-inch wooden stave pipes which have served the Ballard community since the 1930’s. The new pipe will meet north Seattle’s wastewater conveyance needs through the end of the century.

Wastewater from homes and businesses in Ballard now flows through the 36-inch siphons and across the bay, moving from the higher elevated pipes on the north side of the canal to the lower elevation on the south side, for treatment at the West Point Treatment Plant in Magnolia.

Project schedule

August 2011

Mobilize site
Traffic detours begin on Shilshole Avenue Northwest and West Commodore Way

Fall 2011

Site preparation
Existing building demolished
Shaft shoring installed

Fall 2011 Summer 2012

Tunnel Boring Machine shafts excavated
Summer/Early Fall 2012
Junction structure constructed
(West Commodore Road closed)

Summer 2012 Winter 2013

Tunneling

Spring – Summer 2013

Regulator structure added

Fall 2013

Existing siphon relined
New siphon connected to conveyance system

December 2013

Complete restoration
Final inspection
Project closeout

What to Expect

  • Noise and other activity typical of a construction site at the intersection of Shilshole Avenue Northwest and Northwest 20th Avenue in Ballard and at the intersection of West Commodore Way and 24th Avenue West in Interbay.
  • Crews, trucks and heavy equipment at the Ballard and Interbay sites
  • Traffic detours near the construction sites on Shilshole Avenue Northwest and West Commodore Way.
  • Increased truck traffic on Shilshole Avenue Northwest, 15th Avenue Northwest, Northwest Leary Street, West Nickerson Street and Aurora Avenue.

Project updates

News releases

More information

Related project