Brightwater Wastewater Treatment Plant

King County is building the Brightwater wastewater treatment plant at a site in unincorporated Snohomish County (image below is not to scale).

Site plan of the Brightwater Treatment Plant - click image for larger version (PDF file)

The 114-acre site is located at the intersection of State Route-9 and SR-522, just north of Woodinville. Treatment and support facilities will cover approximately 43 acres, with additional area for stormwater treatment, open space, wildlife habitat and wetlands. View larger image (PDF) of site plan.

Treatment Plant Design

The plant design integrates landscape, architecture, wildlife habitat, engineering, art, and education. The goal is to enhance the local community and add wastewater treatment capacity for our region.

When the treatment plant starts operations in 2011, it will have the capacity to treat an average of 36 million gallons of wastewater per day (mgd). By 2040, treatment capacity will be expanded to 54 million mgd. These capacities are for average wet-weather flows (AWWF). The plant must also be able to accommodate peak hourly flows of 130 mgd at start-up and 170 mgd by 2040.

Summary of Treatment Plant Alternatives Design Capacities

 

Route 9 base design & size

Year 2012
  AWWF
  Peak Flow


36 mgd
130 mgd

Year 2040
  AWWF
  Peak Flow


54 mgd
170 mgd

The treatment plant site will include:

  • Wastewater treatment systems
  • Biosolids production
  • Advanced treatment of nearly all flows to Class A reclaimed water standards
  • A state-of-the-art odor control system
  • Attractively designed facilities that blend in with the surrounding neighborhood.
  • An Environmental Education and Community Center and more than 40 acres of open space, restored habitat and trails for public use at the north end of the site.

The Wastewater Treatment Process

Preliminary

Preliminary treatment removes large objects from the untreated wastewater (influent) as it enters the treatment plant. The equipment includes screens for removing debris and grit facilities for removing sand, gravel and other inorganic matter. The screening and grit removal equipment will be covered and vented for odor control.

Primary

Primary treatment is the process where most of the suspended solids settle out of the wastewater. The conventional primary system consists of rectangular clarifier units equipped with collection systems on the top and bottom. Most of the flows coming into the plant wil be treated here. As with the preliminary process, the primary clarifiers will be covered and the air will be vented to an odor control system.

Secondary Treatment - Membrane Bio-reactor (MBR) technology

Secondary treatment is the process where soluble and fine suspended dissolved materials not already removed at primary treatment are removed. As an alternative to conventional secondary processes (knows as conventional activated sludge), the Brightwater project will use Membrane Bioreactor (MBR) technology.

The MBR process includes:

  • Fine screens which remove remaining debris and inorganic material larger than 2 mm from the wastewater
  • Aeration basins that promote the growth of microorganisms that consume organic matter, thereby creating wastewater that has less organic matter that can decompose
  • Membrane tanks, which separate the liquids from the solids

>>>> Learn more about the MBR system being used at Brighwater

MBR treatment at Brightwater

MBR technology provides substantially better effluent quality than conventional secondary treatment. MBR effluent is suitable for irrigation of golf courses, playfields, and for industrial heating and cooling.

Split Flows

During times of high flows, flows above a certain design threshold will be split off after preliminary treatment, processed using an enhanced primary treatment and recombined with MBR effluent for disinfection and discharge to Puget Sound. As with the MBR effluent, this combined effluent also provides substantially better effluent quality than conventional secondary treatment.

Disinfection

The purpose of disinfection is to kill remaining pathogens in the effluent to a level that complies with water quality discharge permits. At Brightwater sodium hypochlorite will be used for disinfection.

Odor Control

King County is committed to operating Brightwater with no detectable odors. Stringent design and performance criteria have been established for odor prevention at the facility. All treatment facilities will be covered, including the influent wet well, screening and grit handling, primary clarifiers, aeration basins, membrane tanks, and disinfection. The headworks and solids handling equipment will also be fully enclosed.

Air is collected from these enclosed areas and is then routed to the odor control systems. This air is then treated by multistage chemical and biological scrubbers, followed by a final polishing stage of carbon adsorption. Each stage treats the process air to a greater degree.

Reclaimed Water

Washington state identifies standards for four classes of reclaimed water, with Class A being the highest. Class A reclaimed water can be safely used for many purposes that do not require drinking water, such as industrial processes; irrigation of edible crops, gardens and landscaping; and irrigation of public areas such as parks and recreational fields.

When it comes online, Brightwater will produce about 7 million gallons of Class A reclaimed water each day for off-site uses, and eventually up to 21 million gallons per day as demand requires. The reclaimed water will also be used on-site for irrigation, tank cleaning, and other processes that do not require potable water.

Learn more about Brightwater reclaimed water construction and about the county's reclaimed water program.

Biosolids

Biosolids are the nutrient-rich organic material produced by treating wastewater solids. After processing and treatment, they can be beneficially recycled as a fertilizer and soil amendment. King County has been safely recycling biosolids for more than 25 years. In 2002, 27,000 dry tons of biosolids from the county's two regional treatment plants were used for agriculture and forestry applications, and a portion was composted for use in landscaping and gardening.

Biosolids production will include thickening, anaerobic digestion and dewatering of the wastewater solids. The stabilized, dewatered biosolids will then be hauled offsite and beneficially used along with biosolids from the West Point and South Treatment lants. The biosolids facilities will have odor control systems.

Related information

Staging the 48” and 66” Forcemain Pipes onto the Pipe Carrier in the Treatment Plant Portal to be transported into the Tunnel for installation -- click to view more photos
View project photos

Installation of membrane bioreactor filters (MBRs) at the treatment plant (April 2011)
View project videos

Contact us if you need more information about Brightwater

King County Brightwater Project

22505 State Route 9
Woodinville, WA 98072
E-mail: Brightwater
Phone: 206-263-9453
TTY Relay: 711