Brightwater construction contracts

Brightwater Treatment System Banner

>>> to construction activities

Brightwater construction contracts

The King County (Washington, USA) Wastewater Treatment Division is making major improvements to its regional sewage treatment system, which are needed to handle rapid population growth in the greater Seattle/Puget Sound region. The center piece of these improvements is the Brightwater Project which will consist of a 36MGD ADF Wastewater Treatment Plant utilizing MBR technology and the associated conveyance system and marine outfall.

This page provides information about the major construction contracts for the Brightwater Project. Please note that most of the contracts have already been awarded. Also, many smaller contracts for construction, consultant services, and goods and services are not listed here. King County's procurement process is administered by the Procurement and Contract Services Section: (http://www.kingcounty.gov/operations/procurement.aspx). Check there for more procurement and contract information.

For current construction information and to sign up for project construction updates, see the project's construction activities web page.

Future Construction Contracts

Name

Description

Contract Amount
($ million)

Expected Solicitation

Expected construction start

Approx. construction duration/ completion date

Ballinger / North Kenmore Facilities

Above-grade odor control facilities, landscaping, and buildings at Ballinger Way and North Kenmore portal sites.

$9.5

Late 2008

Mid 2009

1.5 years


 

Ongoing Construction Contracts - Treatment Plant

Contract

Original Contract Amount ($ million)

Contractor contact info

Expected completion

Treatment plant contracts, including liquids stream facilities, site preparation, earthwork, and north mitigation area work have been awarded to Hoffman Construction Company under a General Contractor/Construction Manager (GCCM) contract.

$73.32

Dave Johnson, Project Manager 425-984-6338

late 2010

Solids Stream /Ordor Control Contract (a design-bid-build contract) has been award to Kiewit-Pacific Co.

166.459

Steve Caniglia
425-354-2420

late 2010


Ongoing Construction Contracts - Conveyance

Contract

Original Contract Amount
($ million)

Contractor contact info

Expected completion

West Tunnel contractor is Jay Dee / Coluccio / Taisei. Includes construction of approx. 21,100 feet of 13 ft. min ID tunnel; 540 ft. of 84-inch microtunneled line; a 35 feet deep portal and sampling facility.

102.45

206-542-2865

early 2011

Central Tunnel contractor is Vinci Parsons Frontier Kemper. Includes two tunnels, approx. 11,600 feet and 20,100 feet long, piping, approx. 3,400 LF influent sewer (microtunnel and open cut) 36 to 48 ID, portal structures at North Kenmore and Ballinger Way portal sites.

211

Lionel Suquet
425 286 1600

late 2010

East Tunnel contractor is Kenny Shea Traylor. Includes approx. 14,000 LF of 16 feet ID tunnel containing pipes and fiber optics cables, construction of launch &, pump station excavation & shoring, and 2,400 LF microtunnel.

130.85

John Kennedy,
425-486-2490

late 2009

Influent Pump Station (IPS) contractor is Kiewit Pacific Co. for construction of 130-mgd pump station expandable to 170 mgd, including approx. 10,000 SF above-grade building, influent structure, generator and chemical buildings, odor control, installation of pumps, generators, electrical, equipment control, and related systems; site work and utilities; testing and start-up of IPS and off-site conveyance facilities.

91.86

Steve Caniglia,
425-255-8333

mid 2011

North Creek Facilities contractor is James W Fowler. Includes construction 72-inch North Creek connector and associated diversion, drop and flow monitoring structures, 30-inch reuse water main with pump station modifications connecting the IPS and North Creek pump station, odor control facilities, mechanical and control installations.

10.18

Michael McMilan,
425-485-4971

early 2009

Hollywood PS upgrade contractor is McClure and Sons. Work includes a chemical injection facility, standby generator, site backflow preventer, vault rehabilitation, landscaping and site improvements.

1.156

Dustin McClure,
425-745-0124

mid 2008

Marine Outfall contractor is Triton Marine Construction, under a design-build contract. Project includes a 5,420 foot long pipe and diffuser to discharge treated effluent into the Sound about a mile off-shore at a depth of approximately 600 feet. Their proposal includes 417 feet of 84-inch steel pipe and 5,018 feet of twin 63-inch HDPE pipes (placed using the controlled submergence method) with staggered 250 foot long diffusers.

27.599 including incentives & allowances

Jon Archer
360-373-7090

late 2010

>>> to construction activities