Kamber Road sewer line repairCompleted summer 2005 During June 2005, the King County Wastewater Treatment Division repaired a 21-inch sewer line along Kamber Road in Bellevue next to East Creek. Repairs to the county sewer were necessary because of ground settling between Richards Road and 137th Avenue Southeast. The county repairs protect public health and the environment.

|
Detour Route King County and Wilder Construction will use the same detour route outlined by the City of Bellevue in its May 2005 Update. Click map for larger view (also available as a PDF file). | The Project The City of Bellevue is making utility and roadway improvements on Kamber Road. King County repaired its sewer line so the city can begin its work. To keep the city project on schedule King County finished repairing the sewer line and the city is beginning its work. All work must be done between June and September. Project schedule King County finished the repairs July 1st and the city has started its work. For more information
|