Bellevue Pump Station Upgrade & Force Main InstallationPump Station  Bellevue Pump Station. Proposed new pump station design (JPEG).
 November 2009 - Future site of newly upgraded Bellevue Pump Station (PDF).
 October 2009 - Demolition of the existing pump station and generator building will occur this month. SE 6th St (in the foreground) is closed for the duration of the project. Click for larger version (JPEG file).
Phase One. During phase one of the upgrade, a new 5,300-foot-long, 24-inch-diameter pipe was installed from the Bellevue Pump Station directly to the Eastside Interceptor, a large regional pipe near Interstate 405. The force main project was completed in March 2008. Phase Two. Over the next two years, the above grade pump station will be demolished and replaced with a facility featuring more powerful pumps, a new generator building, stronger odor control equipment and updated architecture. Upon completion, the refurbished pump station will be able to convey more than 13 million gallons of wastewater daily from west and central Bellevue to King County's South Treatment Plant in Renton -- a 60 percent increase in capacity.
|