Map of Construction Area, February 2002-March 2003
The King County Wastewater Treatment Division has completed a sewer improvement project in downtown Renton to restore lost capacity to the pipeline that carries wastewater from Eastside communities to the South Treatment Plant in Renton. Lost capacity was the result of repairs following the 1965 earthquake.
King County worked closely with the City of Renton and residents in the immediate construction area to reduce the negative impacts of noise, vibrations, truck traffic and street closures during the 12-month construction project. The project mostly affected sections of Houser Way South and Morris Avenue South.
Construction timeline
February-May 2002: Prepared and excavated access pits.
June-September 2002: Tunneled new sewer pipeline between access pits.
October-December 2002: Installed new city water and stormwater pipes.
February-March 2003: Repaved neighborhood streets and completed project.