Project milestones schedule Green River Stormwater Retrofit Planning Project
| Data collection, analysis and modeling |
| Nov. 2010 |
Project Management Core Team to hold all-team project workshop |
| Jan. 2011 |
Approve Quality Assurance Project Plan (956 Kb Acrobat pdf) (Task 1) |
| Feb. 2011 |
Coordinate with WRIA 9 (Task 3) |
| Mar.2011 |
Continuous monitoring could be extended through April, 2011. |
| Apr. 2011 |
Public project input and feedback meeting/workshop |
| May 2011 |
Complete and deliver Existing Data Review Report (Task 4) |
| Sept. 2011 |
Complete In-stream Flow and Water Quality Goals literature review (Task 6). Complete survey of low-flow data (Task 5) |
| Nov. 2011 |
Host public meeting(s) on project status (Task 11) Coordinate with WRIA 9 Forum (Task 3) |
| Dec. 2011 |
Complete New Flow Data Collection Report (Task 5) |
| May 2012 |
Complete and deliver In-Stream Flow and Water Quality Goals Report (Task 6) Complete Watershed Modeling and Report (Task 7) |
| Model analysis and output |
| Sept. 2012 |
Complete SUSTAIN Modeling and Report (Task 8) |
| Report preparation and delivery |
| Nov. 2012 |
Host public meeting(s) on project status (Task 11) Coordinate with WRIA 9 Forum (Task 3) |
| June 2013 |
Deliver completed Watershed Retrofit Plan Report (Task 9) |
| Model marketing & delivery |
| Nov. 2013 |
Host public meeting(s) on project status (Task 11) and coordinate with WRIA 9 Forum (Task 3) |
| Dec. 2013 |
Complete project results presentation (Task 11). Deliver completed Stormwater Retrofit Cost Estimate for Puget Sound and Report (Task 10) | For more information about the Stormwater Retrofit Project, please contact Jim Simmonds, Project Manager, Science and Technical Support Section.
|