March 6, 2007
Wastewater infrastructure investments a major priority in 2007
Continuing its forward-thinking program to ensure the regional sewer
system functions reliably and keeps pace with growth, King County’s
Wastewater Treatment Division will invest $230 million this year in
nearly a dozen major capital improvement projects and numerous smaller
ones that will protect public health and water quality over the next
several years.
Projects include upgrading and
replacing aging facilities, expanding existing ones and building new
facilities such as the Brightwater treatment system to provide enough
capacity for the region’s growing population. Planned projects will
also include controlling combined sewer overflows, cleaning up
contaminated sediment in the Duwamish River and Elliot Bay, and
continuing construction on a pipeline and facilities to distribute
reclaimed water in the Sammamish Valley.
Major construction and design projects scheduled for 2007 throughout
the system include:
East King County
Carnation Wastewater Treatment Facility:Construction is
now under way on a wastewater treatment facility to replace failing
septic systems in the City of Carnation. In addition to the treatment
plant, the county will also begin construction on the companion
Chinook Bend Wetlands Enhancement project, which will use the highly
treated reclaimed water produced at the new plant to enhance and
improve habitat in the Chinook Bend Natural Area. The Chinook Bend
Natural Area will serve as the primary discharge point for the
plant, which is scheduled to begin operating in 2008. Expenditures
this year are expected to be $13.5 million.
Juanita Bay Pump Station Replacement Project: The county plans
to spend about $11 million to continue work on a new 30.6 million-gallon-a-day
pump station in north Kirkland, which will provide additional capacity
to serve growth in this portion of the system. The pump station
will be 70 feet deep and will include three underground levels
to house pumping and electrical equipment.
Bellevue Pump Station Upgrade: The county expects
to solicit bids and select a contractor to upgrade an aging pump
station in west Bellevue and build a new 5,500-foot-long, 24-inch-diameter
force main for carrying wastewater for treatment at South Plant
in Renton. The county has budgeted $9.8 million for project-related
expenditures in 2007.
North King County/South Snohomish County
Brightwater: Construction is under way on Brightwater,
the county’s
largest clean-water project in 40 years. King County has budgeted
about $153 million in 2007 for construction on the conveyance system,
which includes a pump station in Bothell and a 14-mile-long wastewater
pipeline that will run 40 to 450 feet below ground from the Brightwater
Treatment Plant north of Woodinville to Point Wells in Shoreline.
In 2007, the county will spend about $50 million as construction
on the treatment plant facilities begins as early as this summer.
County staff will continue working with Snohomish County to secure
building permits. Construction on the Brightwater North Mitigation
Area, located at the north portion of the 114-acre treatment plant
site, will conclude in 2007. This project includes 40 acres of
open space, habitat enhancement, trails and a field house for community
use. Investment in this project from 2006 to 2007 will reach about
$8 million.
Brightwater Reclaimed Water Backbone: Construction continues this
year on a pipeline system to bring reclaimed water produced at
the Brightwater Treatment Plant to irrigators and industrial customers
in north King and south Snohomish counties. The project includes
converting an existing force main into a reclaimed water pipeline
that will run from the North Creek Pump Station in Bothell to the
York Pump Station in Redmond, and installing reclaimed water pipes
in the tunnel being built for the Brightwater conveyance system.
Expenditures are estimated at $1.6 million in 2007.
Hidden Lake Pump Station and Sewer Improvement
Project: This project
in Shoreline will replace King County’s 40-year-old Hidden Lake
Pump Station and 12,000 feet of the Boeing Creek trunk sewer. The
project also includes a 500,000-gallon underground wastewater storage
pipe to prevent overflows to Puget Sound. Additionally, the county
is working with Seattle Public Utilities to replace 5,000 feet
of water mains. The county plans to spend about $15.2 million in
2007 during construction on the new pipelines, the storage facility,
and 6.8-million-gallon-a-day pump station.
Seattle
Combined Sewer Overflow Control: The county will continue its
program to reduce combined sewer overflows, or CSOs, that occur
in older parts of the system during heavy rains, degrading water
quality and posing public health risks. In 2007, King County will
spend about $1.7 million to begin predesign on the Puget Sound
Beaches Project to upgrade pump station facilities and/or increase
storage at the North Beach, Murray and Barton pump stations, and
South Magnolia outfall. The projects will include a siting process
that will enable interested community members to get involved in
some aspects of project planning.
Sediment Management Program: This program enables
King County to proactively address sediment contamination near
combined sewer overflow, or CSO, locations in Puget Sound. Among
planned projects for 2007, the county will work with permitting
and regulatory agencies as planning gets under way on a project
to remove an estimated 17,000 cubic yards of contaminated sediment
at the old Denny Way outfall near Myrtle Edwards Park. Expenditures
for the program are expected to be $2.7 million.
Densmore Drain: The county will install a stilling vault and ventilation
pipe to better control stormwater and prevent overflows into the
Lake Washington Ship Canal and Lake Union. The project will also
include replacing the existing 36-inch-diameter drainpipe with
one that’s more stable and reliable. Construction on this $1.6
million project should be completed this spring.
Lower Duwamish Waterway Cleanup: The county will continue its
commitment to cleaning up contaminated sediments, implementing
source control actions, and complying with agreements with regulators
and local governments. In 2007, the Wastewater Treatment Division
will continue to work with the City of Seattle on the cleanup of
Slip 4, an identified early action area in the Lower Duwamish Waterway.
The $1.6 million investment in 2007 will also include continued
collaboration with the City of Seattle, the Port of Seattle and
The Boeing Company on the Lower Duwamish Waterway Superfund site,
which is part of a long-term cleanup effort.
53rd Avenue Pump Station: Improvements to this Alki Avenue pump
station will increase system reliability and help make the facility
a better neighbor. Planned construction, scheduled to begin in
September, includes installing new odor control equipment, upgrading
the facility’s electrical and mechanical systems, and doubling
the size of the below-ground pump station. The county is now finalizing
design and securing permits needed to begin the project in September.
Expenditures this year are expected to be $3.2 million.
Ballard Siphon: To protect water quality in the Lake Washington
Ship Canal, King County is investing $16.4 million in the Ballard
Siphon Project, which will replace a 70-year-old wooden sewer pipe
that extends across the floor of Salmon Bay near the Hiram M. Chittenden
Locks. In 2007, the county will focus on completing design, securing
permits, and soliciting bids for construction.
King Street Odor Control: In 2007, the county will begin a project
to build a new one-story odor control facility just south of King
Street Station near the Weller Street Bridge. The project will
help improve air quality in south Pioneer Square by reducing or
eliminating odors from the Elliot Bay Interceptor, a large sewer
pipe that carries wastewater from south Seattle through the downtown
area to West Point Treatment Plant. Expenditures this year are
expected to be $1.1 million.
Murray Avenue Pump Station: This year, King County will spend
$1.2 million upgrading the electrical system in this West Seattle
pump station. The county will also finalize design on a structure
for new odor control and emergency generator equipment, which will
incorporate the design guidelines established with the help of
local community members.
South King County
Fairwood Interceptor: King County will soon complete
a project that began in 2000 to re-route and replace an aging pipeline
in an area prone to erosion and landslides, and to improve water
quality and slope stability around Madsen Creek. The project also
included upsizing pipes to increase system capacity in the area.
The county expects to invest $900,000 this year to complete construction
of the project and to restore roads, sidewalks and public rights-of-way
that were disturbed by the earlier construction work
Kent/Auburn Conveyance System Improvement
Project: This project
will expand capacity in the rapidly growing south portion of King
County’s service area by adding approximately five miles of 18-to
54-inch-diameter pipes in Kent, Auburn, Algona and Pacific. Construction
is scheduled to start in 2008 and conclude in 2010. The county
plans to spend about $3 million on design work in 2007.
Black Diamond Wastewater Storage Facility: In 2007, the county
will begin design on an underground wastewater storage facility
in the City of Black Diamond that will extend the life of existing
equipment and defer the need to build additional new pumping facilities
for several years. The county plans to spend about $1 million of
the project’s overall $5 million budget this year.
Regionwide
Regional Infiltration and Inflow (I/I) Control
Program Implementation: The county is working cooperatively with local sewer agencies to
implement the Regional I/I Control Program, which was approved
by the King County Council in 2006. I/I is clean water that gets
into the sewer system from leaky pipes or manholes on private property
or local sewer systems during rainy weather, taking up capacity
needed for wastewater conveyance and treatment. In 2007, the county
will begin work on at least two projects to reduce the volume of
I/I that gets into the sewer system. By investing $25 million in
these projects over two years, the county hopes to find cost-effective
ways to reduce I/I and save ratepayers money over time by not having
to build new facilities to accommodate these flows.
For more information
Other information about
wastewater construction projects and programs is available on the
Web site for the Wastewater
Treatment Division:
The wastewater treatment system operated by King County now includes
348 miles of sewer lines, 47 wastewater pump stations, three stormwater
treatment plants, a treatment plant on Vashon Island, two regional
treatment plants in Renton and Seattle, and two new treatment plants
under construction in south Snohomish County and the City of Carnation.
The system now serves 1.4 million people across a 420-square-mile
area in the central Puget Sound region including parts of Snohomish
and Pierce counties.
Formerly called Metro, the regional public utility has been preventing
water pollution for more than 40 years.