April 24, 2006
Bid for Brightwater tunneling project $20 million below estimate
King County's wastewater utility ratepayers got encouraging
news last week when bids on a contract to build the central portion
of a 13-mile conveyance pipeline for the Brightwater project came
in significantly lower than the engineers' estimate.
“We had five bidders, which is extremely competitive given
the complexity of the project,” said Don Theiler, Director
of the Wastewater Treatment Division. “At this point, we've
received bids for the majority of Brightwater tunnel work and so
far they've all been under budget. This is great news as we
work hard to keep this project on budget.”
The apparent low bid submitted by Vinci/Parsons RCI/Frontier-Kemper,
a Joint Venture, based in Montreal, Canada, was $209.7 million compared
to King County's estimate of $229.9 million. The remaining bids
ranged between $216.9 and $257.6 million.
The scope of work will include building two tunnels, one from Kenmore
to the North Creek Business Park in Bothell and another from Kenmore
to Ballinger Way Northeast in Shoreline. The combined length of
the tunnels will be about 32,0000 feet.
The selected contractor will dig the 16-foot-diameter tunnels using
two larges machines that can work long distances underground without
disrupting the surface.
The contractor will also excavate two deep shafts, one near the
intersection of 80th Avenue Northeast and Northeast 192nd street
in Kenmore and another along Ballinger Way Northeast in Shoreline,
for launching and removing the tunnel-boring machines. The contractor
will install six pipes in the tunnel ranging from 14 inches to 126
inches in diameter along with two fiber-optic cables to monitor
Brightwater facilities. The tunnel will be filled with concrete
after those installations. In addition, the contractor will trench
a smaller 4,200-foot-long pipeline from the Kenmore portal to connect
the new Brightwater pipes to the existing sewer system.
Theiler said that this competitive bid comes on top of design efforts
that substantially lowered project costs from previous estimates.
“We undertook a major effort to reduce the cost of this project
before the bids were solicited,” said Theiler. “A value
engineering review panel made several cost-saving recommendations,
including combining a separate influent and effluent tunnel into
a single tunnel, which reduced project costs by $30 million.”
The county and its consultants will thoroughly review the bidder's
qualifications before awarding the contract. Construction is scheduled
to begin as early as July 2006.
The county has already selected Jacobs Civil to provide construction
management services for the conveyance facilities. MWH/Jacobs Associates
is designing the system as a joint venture, and CDM conducted geotechnical
work as part of tunnel design.
Brightwater tunnel construction has been underway since March on
the east segment of the conveyance system. Kenny/Shea/Traylor was
awarded the contract to build the Brightwater tunnel from North
Creek to the treatment plant site on Route 9 in December.
More information about the Brightwater project, including the status
of construction-related contracts, is available on the project Web
site at http://dnr.metrokc.gov/wtd/brightwater/index.htm.
People enjoy clean water and a healthy environment because of King
County's wastewater treatment program. The county's Wastewater
Treatment Division protects public health and water quality by serving
17 cities, 17 local sewer utilities and more than 1.4 million residents
in King, Snohomish and Pierce counties. Formerly called Metro, the
regional clean-water agency now operated by King County has been
preventing water pollution for more than 40 years.