March 30

This week crews excavated 1/3 of the unsuitable soils. By April 1, they expect to place toe rock which will give them the foundation to start building the slope back up for next week.

Slide repair work.
Slide repair work on NE 124th Street. March 30, 2017. Photographer: Daisy Dailey.

Slide repair work.
Slide repair work on NE 124th Street. March 30, 2017. Photographer: Daisy Dailey.

March 27

Slide repair work along NE 124th Street continues. Over the weekend crews removed brush and asphalt, and created a platform/access ramp for the excavator and dump trucks to reach the lower elevations. This week they will remove unsuitable soil and place rock to stabilize the slope.

Slide repair site.
March 25 photo of weekend work at the slide repair site.

March 24

Crews began slide repairs on NE 124th Street on March 23. The first day of work included removing trees and extending pipe for a wider lane through the work zone. The work runs Monday through Saturday, from about 7:30 a.m. to 5:30 p.m. Motorists should expect midday road closures up to 30 minutes. Flaggers will direct motorists through the work zone. The repair work will last about three and a half weeks.

Tree removal
Crew removed trees to prepare for slide repairs along NE 124th Street. March 23, 2017. Photographer: Daisy Dailey.

Extending pipe.
Cooperative weather made it possible for crews to extend pipe for a wider lane through the work zone. March 23, 2017. Photographer: Daisy Dailey.

Flagging traffic.
Flagging traffic through the work zone on the first day of the slide repairs. March 23, 2017. Photographer: Daisy Dailey.

March 22

Beginning Thursday, March 23, crews will begin slide repairs on NE 124th Street. The work will take place daily from about 7:30 a.m. to 5:30 p.m., Monday through Saturday. No work will be conducted on Sundays. Motorists should expect midday road closures up to 30 minutes. Flaggers will be on site. The work is expected to take approximately three and a half weeks.

March 21

Crews will be onsite this week working on staging areas for equipment. This includes prepping the shoulder areas with gravel and mobilizing construction equipment. We will let you know when the repair work is expected to begin.

Staging area for NE 124th Street slide repair work.


March 17

On Monday, March 20th, crews will stage equipment near NE 124th Street in preparation for repairs. We will keep you updated on when repair work is anticipated to begin.

March 14

Roads is working on the necessary temporary road construction easements and permits. We will keep you updated on when repairs will begin.

March 10

Today crews replaced two stop signs at each end of the slide area along NE 124th Street with temporary traffic signals. The signals will regulate traffic through the one lane restriction. We will keep you updated on when repair work along NE 124th Street is anticipated to begin.

Temporary traffic signal
Temporary traffic signal on NE 124th Street.

March 9

Expect to see crews today at NE 124th Street. They will evaluate site placement for two temporary traffic signals. The signals will be installed on Friday, March 10 in each direction to regulate traffic through the one lane restriction. A flyer box is also at the site which contains Roads contact information and a link to this webpage.

Flyer box
Flyer box for NE 124th Street slide information.

March 8

On Friday, March 10th, crews will install a temporary traffic signal in each direction to regulate traffic through the one lane restriction. They will replace stop signs at each end of the slide area along NE 124th Street and will be operational by mid-day Friday. Engineering staff are still finalizing repair plans and coordinating equipment, materials and staff. We will keep you updated on when the repair work is anticipated to begin. Roads staff have been in continued communication with the school district and fire district to coordinate efforts.

Temporary traffic signal
A temporary traffic signal similar to the one pictured above will be installed along NE 124th Street on March 10th.

March 7

Engineers have evaluated the samples collected from the February 25th and 26th geotechnical drilling that took place along NE 124th Street. Design plans are being finalized and we expect to know more tomorrow (March 8). We will post an update when we receive the information.


March 3

NEW: Sign-up for email updates to receive the latest information about NE 124th Street. Click the red button to the right on this page to sign-up. Add your email, select your subscription type (email or text message) and click Confirm. You will be instantly added to the NE 124th Street email group.


February 28

The geotechnical drilling work along NE 124th Street is complete. Samples were collected last Saturday and Sunday. Geotechnical engineers are now analyzing the samples to determine next steps. The roadway remains restricted to one lane with resident access only.


February 26

Additional geotechnical drilling will take place on Sunday, February 26th along NE 124th Street to collect samples. The work will finish at approximately 3 p.m. No lane closures are expected.

February, 26, 2017.
Prep for geotechnical core sample collection.

February, 26, 2017.
Collecting core samples.

February, 26, 2017.
Sheeting over damaged road.


February 25

New photos:

Engineers setting up their Geotechnical work station to log samples from NE 124th Street. February, 25, 2017.
Engineers setting up their Geotechnical work station to log samples from NE 124th Street. February, 25, 2017.

Core drilling bits by the drilling machine along NE 124th Street. February 25, 2017.
Core drilling bits by the drilling machine along NE 124th Street. February 25, 2017.

Contractors and County employees drilling core samples along NE 124th Street. February 25, 2017.
Contractors and County employees drilling core samples along NE 124th Street. February 25, 2017.

Samples being collected from the geotechnical drilling along NE 124th Street. February 25, 2017.
Samples being collected from the geotechnical drilling along NE 124th Street. February 25, 2017.


February 24

Reminder: On Saturday, February 25, expect up to 60 minute delays from 8:30 a.m. to 2 p.m. On that day, engineers will conduct geotechnical drilling. They will collect core samples to determine next steps. In addition, the normal school bus route will resume beginning Tuesday, February 28.

February 24 photo of temporary repairs on NE 124th Street.
Temporary repairs along NE 124th Street include a diversion pipe (seen in the bottom left corner) that is keeping water from going under the road. A new temporary shoulder is also in place to help keep one lane open. February 24, 2017.


February 22

New photos:

Crews adding temporary drainage repairs on the hill side of NE 124th Street. February 22, 2017.
Crews adding temporary drainage repairs on the hill side of NE 124th Street. February 22, 2017.

Temporary drainage repairs on the hill side of NE 124th Street. February 22, 2017.
Temporary drainage repairs on the hill side of NE 124th Street. February 22, 2017.


February 21

Beginning Wednesday, February 22, full road closures will take place on NE 124th Street east of Highway 203 and near Duvall for emergency drainage repair work. From February 22-24, expect up to 30 minute delays from approximately 8:30 a.m. to 2 p.m. The closures involve adding additional temporary drainage repairs on the hill side of the road. On Saturday, February 25, expect up to 60 minute delays from 8:30 a.m. to 2 p.m. On that day, engineers will conduct geotechnical drilling to determine next steps for permanent repairs.

Feb. 20 photo of the NE 124th Street damage
Temporary repairs in place along NE 124th Street. Photo: February 20, 2017.


February 17

Crews are closely monitoring NE 124th Street and assessing the damage. The roadway is restricted to one lane with resident access only, but it could close unexpectedly. The county is coordinating with emergency responders. Red Cross and other support services are available should they be needed.

For updates on this slide and road access, please continue to visit this page and the My Commute page which provides road closure updates and maps. The public can also call the 24/7 Road Helpline for updates and to report road maintenance and traffic safety issues in unincorporated King County — 24 hours a day, 7 days a week, 365 days a year. 206-477-8100 or 1-800-527-6237 (1-800-KC-ROADS).

Photo of the NE 124th Street damage, 8 hours later
Photo on the left: 3pm on Feb. 16, 2017. Photo on right: 11pm the same day.
Call us:

206-477-8100 or 1-800-527-6237 (1-800-KC-ROADS)

Questions?

Send us an email.