Target days Total permits Average days # within target % within target # outside target
Residential model homes (Basics) 90 208 36 177 85% 31
Residential custom homes 90 164 64 130 79% 34
Residential minor additions 15 36 2 35 97% 1
New commercial buildings 120 28 113 17 61% 11
Commercial tenant improvements 120 28 36 27 96% 1

*Key permits are individual permit types that are considered representative of major construction groups.

ALL PERMITS BY CLOCK TARGET*
2011
Total permits Average days # within target % within target # outside target
All building permits with 15 day target 36 2 35 97% 1
All building permits with 40 day target 454 25 346 76% 108
All building permits with 90 day target 626 52 507 81% 119
All building permits with 120 day target 1,493 13 1,468 98% 25
Totals 2,609

*Excludes less than 1% of permits that did not have targets assigned.

Land Use Services


KEY PERMITS*
2011
Target days Total permits Average days # within target % within target # outside target
Conditional use 120 6 77 6 100% 0
Preliminary plats 150 3 114 3 100% 0
Preliminary short plats 120 15 89 12 80% 3
Lot line adjustments 120 51 18 49 96% 2
Right-of-way 120 10 73 8 80% 2
Clearing/Grading 45 23 43 16 70% 7
Clearing/Grading 90 589 83 518 88% 71

*Key permits are individual permit types that are considered representative of major construction groups.

ALL PERMITS BY CLOCK TARGET*
2011
Total permits Average days # within target % within target # outside target
All land use permits with 45 day target 25 42 18 72% 7
All land use permits with 90 day target 588 83 517 88% 71
All land use permits with 120 day target 159 147 132 83% 27
All land use permits with 150 day target 6 115 5 83% 1
Totals 778