Skip to main content
King County logo
KEY PERMITS* 2007 Target days Total permits Mutually agreed time extension Average days # within target % within target # outside target
Residential model homes (Basics) 90 759 3 758 100% 1
Residential custom homes 90 629 60 527 84% 102
Residential minor additions 15 458 10 357 78% 101
New commercial buildings 120 47 95 36 77% 11
Multi-family housing 120 7 152 2 29% 5
Commercial tenant improvements 120 59 26 59 100% 0

*Key permits are individual permit types that are considered representative of major construction groups.

ALL PERMITS BY CLOCK TARGET* 2007 Total permits Mutually agreed time extension Average days # within target % within target # outside target
All building permits with 15 day target 463 21 360 78% 103
All building permits with 40 day target 711 50 402 57% 309
All building permits with 90 day target 1921 43 1793 93% 128
All building permits with 120 day target 2921 62 2869 98% 52
Totals 6016

*Excludes less than 1% of permits that did not have targets assigned.

Land Use Services

KEY PERMITS* 2007 Target days Total permits Mutually agreed time extension Average days # within target % within target # outside target
Conditional use 120 17 96 15 88% 2
Preliminary plats 150 19 136 12 63% 7
Preliminary short plats 120 67 85 57 85% 10
Lot line adjustments 120 83 27 82 99% 1
Right-of-way 120 24 75 17 71% 7
Clearing/Grading 45 3 14 3 100% 0
Clearing/Grading 90 461 25 441 96% 20

*Key permits are individual permit types that are considered representative of major construction groups.

ALL PERMITS BY CLOCK TARGET* 2007 Total permits Mutually agreed time extension Average days # within target % within target # outside target
All land use permits with 45 day target 3 14 3 100% 0
All land use permits with 90 day target 461 24.5 441 96% 20
All land use permits with 120 day target 498 84 418 84% 80
All land use permits with 150 day target 23 110 16 70% 7
Totals 985

*Excludes less than 1% of permits that did not have targets assigned.